____________________
__________

Welcome to our Re-construction phase. Keep checking back for updates as we finish up the remodel of our Facilities Planning (Architectural/ Engineering) division... And as we continue with the remodel of the CS (Computer Services), and GS (Graphic Services) areas.

We had a group of guys here that call themselves Steppin' Out Ministries, who took care of the main indoor renovations, and will be intermittently back to help rebuild and tear down as needed/ or funds allow. On the outside, we had High Touch Ministries doing the initial dirt work and grading. This team consists of, well, Darren... and his bionic mechanical, appendage extensions.

Please forgive the lack of "before" shots, hopefully I'll be able to find some later on, and hopefully things will begin to make sense as the days and hours progress.

Note: If you are unfamiliar w/ TECH and our layout, I have tried to be fairly descriptive and orderly...

The most recent post will be at the TOP. The beginning posts are in the Archive section on the Right, under 2008 and January -only so many posts are able to fit on the page- so, if you're looking for how it all started it will be there.
__________
____________________

Thursday, March 6, 2008

Week 6 March 3-7



Mar 3-5: Library Shelving Assembled, Books Organized, Carpet Removed.







Mar 6: Carpet Adhesive Removed, Laminate Flooring Installed
10:30am [North side, facing West (WNW actually, but you get the idea)]


3:17pm: N side, facing NE


5:00pm: N side, facing W


10:30am: West sieede, facing SSW


Because the Carpet Adhesive couldn't make amends w/ the Vinyl Planking Adhesive, it was decided that the Carpet Adhesive should graciously yield to the incumbent flooring, seeing as the travel expenses had already been spent. All seemed well until CA received what appeared to be a very nasty email from VPA, which actually turned out to have been sent by the Old Armsrtong Vinyl from the bathrooms down the hall ('cause OAV was being asked to leave also). So both OAV, and the mistaken CA, dug in thier heels and were forced to leave under duress w/ solvents and heavy sharp metal objects. Since CA was spread over such a wide area, it was less fortified in its efforts to defend its territory, but still required extra man hours, and the purchase of industrial adhesive removers; OAV, because of its compact area proved to be a bit more formidable, and proceeded to "just [make] a general mess of things". Needless to say, these actions necessitated the revocation of both CA & OAV's equity accounts, and lease deposits. The emotionally grieved VA, has been compensated by the waiving of any entrance, or lisenceing fees, and will not be charged room & board.

In good faith, VPA has decided to send letters of contact to both CA & OAV in attempt at resolving any matters of dissent, to which no response has been forthcoming as of yet. We hope each party can reconcile any and all misunderstandings in a timely, and Christian manner. We also appreciate your concern in this matter. -Ed.

Loosening the Carpet Adhesive w/ Lacquer Thinner


Scrape it up...


Use your Legs...


Put it in the box...


And here's to hoping that insurance pays for our new Backs!


South Side, facing ESE

Monday, February 25, 2008

Week 5: Feb. 25-29

Feb 25:






Feb 26: Re-Dustification of the Crushed Asphalt




Feb 28: And on to the Front Yard

Just re- grading 'cause we can; no road or parking going around the building...

Tuesday, February 19, 2008

Week 4: Feb. 18-22

Feb. 18:
More dirt, More Leveling


Feb 19:
Old McDonald had a farm E-I-E-I-O... And on his farm he had some... .:Di
rt!:.

In the morning, farmer Darren Schulz... err, McDonald diligently sets about the mornings activities, as he begins the day by harvesting the night's crop of Red Clay...

*Editor's Note: K, just for the record, if this type that you are reading is Humongus... I have no idea what's going on. I did not format it that way. -Joel K*



And by 1:00pm... A bumper crop! We must have some of the fastest growing Dirt in the whole State! We should have a Race... I challenge any other State to produce as much or more Red Clay as we do... Over night. Please comment your entries, I'll sort them, and post a roster...

1.We've got the pole position so far.



New Wallpaper & Vinyl Laminate Flooring in Library


Prepping the old walls... filling seams, and smoothing the drywall joints.

Feb 20: More Art...


Monday, February 11, 2008

Week 3 Feb 11-15


Feb 11: New Stuff: Asphalt Digester! The catfish of the road working world, if you will.






Feb 12:
Rain + Dirt = Squish.

Still crushin' the asphalt though...


Feb 13:






Feb 14th: More Leveling dirt for the Additions' Foundation, Landscaping and new Parking.











Feb 15: More Dirt! More More More!





Thursday, February 7, 2008

Week 2 Feb. 7-8

Yesterdee: (6th)


T'day: (7th)





Here's how he did it...


Wednesday, February 6, 2008

Week 2 Feb. 4-8


There's art everywhere, sometimes you just gotta look.




The pit was filled back in with topsoil, 'cause the dirt/clay that was taken out will pack better for the parking area.


There's a new Gehl in town... This is Darren's newest addition... two speeds, and turbocharched!







Here's a compilation I threw together... it's just a test.

Monday, February 4, 2008

Day 17-ish


Prepping the new Parking area


& the new Retaining Wall