Welcome to our Re-construction phase. Keep checking back for updates as we finish up the remodel of our Facilities Planning (Architectural/ Engineering) division... And as we continue with the remodel of the CS (Computer Services), and GS (Graphic Services) areas.

We had a group of guys here that call themselves Steppin' Out Ministries, who took care of the main indoor renovations, and will be intermittently back to help rebuild and tear down as needed/ or funds allow. On the outside, we had High Touch Ministries doing the initial dirt work and grading. This team consists of, well, Darren... and his bionic mechanical, appendage extensions.

Please forgive the lack of "before" shots, hopefully I'll be able to find some later on, and hopefully things will begin to make sense as the days and hours progress.

Note: If you are unfamiliar w/ TECH and our layout, I have tried to be fairly descriptive and orderly...

The most recent post will be at the TOP. The beginning posts are in the Archive section on the Right, under 2008 and January -only so many posts are able to fit on the page- so, if you're looking for how it all started it will be there.
__________
____________________

Friday, May 29, 2009

Fri. May, 29

Some information you can impress your friends with... 'cause everybody likes to sound intelligent, sometimes: DuPont™ Tyvek® material. You know those wrist bands that you get at the fair/hospital/museum... the "Do not remove if you value your life." tags on pillows... looks and feels like paper, but you can't tear it? Most likely Tyvek®. Here's a link to the StuccoWrap®


DuPont™ Tyvek® StuccoWrap®



Thursday, May 28, 2009

Thur. May, 28


A couple guys...


A couple strong nerves...


A couple sections of 2in conduit, for marking cut lines...


And a couple hours later.

Wednesday, May 27, 2009

Wed. May, 27


~11:00AM


~ 3:30PM Foyer: New Top Cap installed for Windows

Tuesday, May 26, 2009

Tue. May, 26




Rain Delay 2


...but these guys don't care about the rain... cause they're making the thunder!


Doesn't matter though, because when they left– this worked...



Friday, May 22, 2009

Fri. May, 22 (Updated 4:30)


Starting the Lower Wall for the Foyer Windows... (Far Right).




Foyer Window Sill

Thursday, May 21, 2009

Thur. May, 21


Laying out top rail to match base plate.


Top Rail in


Main Beam Fab n Install Sequence


EOD 8: Egg: Mostly Ply'd Outer // Foyer: Top supports & Main Beams in.


Plywood wrap Photo Sequence


Foyer Overhang Photo Sequence

Wednesday, May 20, 2009

Wed. May, 20


Day 7 AM




Moving the Base plate to the edge of the slab.